Storage System Configuration:
1. Battery configuration and calculation
1.1.Battery capacity:
E= (Battery module voltage(V) x Battery module capacity (AH) x Module number/1000) KWH
e.g.:The battery module is 48V/50AH, 4PCS in parallel
E=48V*50AH*4/1000=9.6kwh
1.2. SOC:F
State of charge,Battery total capacity divided by battery remaining capacity.
E.g. 9.6kwh SOC=0.8,E=9.6kwh*0.8=7.68kwh。
1.3. DOD:
Depth of discharge: Percentage rate of battery rated capacity divided by battery discharged capacity.
e.g.:9.6kwh DOD=50%,the discharged capacity E=9.6kwh*50%=4.8kwh。
1.4. Charge Discharge Ratio C:
C:The rated current divided by the current when charging and discharging
e.g.:100AH battery allow 1C discharge,0.5C charge,means discharging current is 100A, charging current is 50A.
1.5. System Storage Design:
1.5.1 General restrictive factor, e.g. the max charge & discharge current shall not be higher than battery charge & discharge ratio C.
1.5.2. Load day power consumption, lasting time, DOD
e.g. load day power consumption Ed=3kwh, lasting time is 2 days, DOD is not over 60%, the energy storage capacity shall be as below:
E=Ed*2/DOD=3kwh*2/60%=10kwh
Verify:For 50V system, battery capacity is 200AH,allowing max 0.25C discharging, the max discharging current is 50A. Then check the peak power of the load to see whether the discharging current is enough, if not,the system storage capacity shall be increased or system voltage can be raised.
2. PV configuration
2.1. Before configure the PV, please check the PV data for PCS:
Take the PV in the table for example:
PV Data |
Max PV Power |
4200W |
5400W |
Max PV Voltage |
580Vdc |
MPPT Voltage Range |
125-550Vdc |
Max DC Current |
15A/15A |
Input Strings/MPPT Tracker |
2/2 ( parallel enabled) |
2.2. Firstly to confirm the system day generation:
Two factors to determine day generation:one is day consumption,the other is feeding in grid ratio
e.g.:day consumption is 10kwh(part of energy will be consumed directly in daylight,the other part will be stroed and used at night),feeding in grid ratio is 30%. System efficiency 95% .
The day generation is Ewp=10kwh/(1-30%)/95%=15kwh(considering system loss)
2.3. Calculate PV system capacity and panel config:
System storage is based on day generation and average sunshine duration:
Wp=Ewp/Hd(Hd is 3.5 hours as an example)=15kwh/3.5h=4.3kw
Then calculate the panels quantity based on the one panel:
N=Wp/We(We is 250Wp as an example)=4.3kw/250w=18PCS
Two independent MPPT Input,9PCS of panels for one string
Verify:
250Wp mono or ploy panel,open circuit voltage is about 43.7V,MPPT voltage is about 37V
Voc(open circuit voltage)=43.7*9=393V
Vmppt=37*9=333V
2.4. Installation
Each MPPT string has below requirement:
–Same model
–Same panel quantity for each string
–Same deployment
–Same angle
3. Determine factor for system power
3.1. Backup Load:
It indicates the loads that need hybrid inverter to power when they are off grid, so the backup load power shall not be higher than the backup power of the hybrid inverter.
3.2. Bypass Load:
It indicates the loads that can be powered up when they are on grid. It depends on the system grid input power, which is our configured MCB and Meter.
4. Load Configuration
4.1. The system has two load terminals: one is for Backup,the other is for Bypass.
Take the PCS in the table for example:
Rated Power |
3.6kva |
4.6kva |
Max Continuous Output Power |
Back-up |
3.6kva |
4.6kva |
Bypass |
5.7kva |
7.3kva |
|
4.1.1. Backup Load is the loads that can be powered up when there is off grid. If there is grid, the loads can be powered up by PV, battery or grid based on the system working mode. When grid is off, the loads will be powered up by the PV, batter.
Backup power depends on the output power of the PCS.
4.1.2. Bypass load is the loads that can be powered up only when there is on grid. And it can be powered up by PV, battery and grid if there is grid. Once grid is off, the bypass load will be powered off.
Bypass power depends on the grid capacity and the internal MCB current.